Friday, 19 July 2019

Week three of the resumption

Well, we have rafters on the roof of the extension.
Workers were on-site for three of the five days. One of those days was when the carpentry firm doing the roof was on-site and they achieved all this on the one day. Not sure what was being done by the others on the other two days. I am not too enthused by the work done over the last three weeks and am currently a bit pessimistic about a completion date.
On the positive side, it does look as the structure will be ready for the window installers in the week beginning August 5th.